PROJECT REPORT
Fallbrook #3

the CONCEPT

The Mission

I first met this couple a few years back, I went and did the initial design consultation, we went back and forward with designs and prices, then they decided to hold off. Fast forward to present day, we’d just finished a pool opposite them, they called out of the blue wanting to move forward.

The Details

They had a giant slope that took up 50% of the yard, so the first order of business was to deal with that. We used a raised bond beam and retaining walls to push it back.

The Challenge (because there always is one)

The challenge? Rock, all of the rock, I don’t think we’ve ever had a harder excavation. Turns out blue granite is very very hard, and difficult to remove. Took us nearly a week to complete an excavation which normally would have been a day.
the REPORT
before & after
DSC07026 DSC01373